Database audit and remediation plan (2026-11-21)

Status: accepted by the product owner on 2026-11-21; Phases 0, 1 and the expand step of Phase 4 in production (§7 tracks what is done; §6 holds the owner's decisions). Audited state: origin/main at migration 0150 (111 tables, 1036 columns, 215 foreign keys, 294 indexes), plus production's catalog statistics and, for Phase 0, counts only (no personal data was read).

The one non-negotiable goal: no production data is lost, not by a migration, not by a fix-up, not by a rollback.

1. Findings in short

What holds: every table has a primary key, every timestamp is timestamptz, no redundant index, partial unique indexes guard the state machines, grades are append-only (supersedes_id), the audit log is immutable by trigger, secrets are stored hashed.

# Finding Severity
F1 ~80 enum-like text columns (state, role, kind…), 7 with a CHECK; users.role, course_staff.role, sessions.kind, attempts.state, gradings.state are guarded by TypeScript only high
F2 Duplicated parent keys never cross-checked: gradings(answer_id, attempt_id, item_id), answers(attempt_id, item_id), project_group_members(project_id, group_id), project_repos(project_id, group_id) high
F3 References without a foreign key: project_repos.{current,frozen,review}_grade_run_id, project_criterion_grades.pass_id, attempts.{last,shown}_item_id medium
F4 E-mail normalization (trim + lowercase) is a convention; the unique keys of enrollments, teacher_grants, user_emails are case-sensitive medium
F5 Points are numeric(6,2) in gradings/project_criterion_grades but float8 in project_repos and project_grade_runs medium
F6 138 ON DELETE CASCADE: deleting a course erases its attempts, grades and projects in one statement; the only way back is a restore product decision
F7 Catch-all tables: projects 58 columns (32 nullable), project_repos 49 (42 nullable): configuration, job leases, sync state, grading, adjustment and the released snapshot in one row. 938,920 updates on 1,069 project_repos rows high
F8 No "activity" entity: the evaluation_id XOR project_id arc is repeated in five tables; contestations and project_contestations mirror each other design (ADR)
F9 notifications keeps its kind in payload->>'kind': ten partial unique indexes, one migration per deduplicated kind low
F10 project_repos.user_id means "owner" for a solo repository and "first to accept" for a group's low
F11 Naming/types: enrollments.nom/prenom, drill_new_unlocks.day as timestamptz, classrooms.period_* as regex-checked text, hashes as char(64) or text low
F12 No plain index on project_repos(project_id) (partial ones only): 21.5 M sequential scans, 17 billion rows read; same gap on grade_dispatches(repo_id), attempts(user_id), answer_acceptances(item_id) medium (grows with use)
F13 No pg_stat_statements, no slow-query log; statement_timeout, lock_timeout, idle_in_transaction_session_timeout all 0 high (blind)
F14 PostgreSQL sized for a 50 MB database (shared_buffers 32 MB, work_mem 2 MB); the database is 172 MB medium
F15 The import_classroom schema (2 tables) left from the merge low

2. Production as measured (2026-11-21)

  • VM: 1 vCPU, 1.9 GB RAM, 0.5 GB of the 2 GB swap in use, 807 MB available. It also hosts the staging stack (its own rootless Docker), the TB application and the RAD portal. Disk 35 % of 38 GB.
  • PostgreSQL 17, 65 MB resident; database 172 MB, of which webhook_deliveries is 61 MB (TOAST, purged at 30 days: fine).
  • Backups: daily pg_dump -Fc (~23 MB, 30 days), off-site borg every night, Hetzner daily VM backup. RPO 24 h.
  • The pre-migration dump is a manual step (deployment guide §6): deploy.sh does not take one. Migrations run at application start, in one transaction (a failed migration rolls back whole).

The third point drives the safety net. A failing migration is harmless. The dangerous one succeeds but transforms data wrongly: every write after it then lands on wrong data, and restoring the last dump loses those writes.

3. Safety rules (every phase)

  1. A dump before every migration, automatically. deploy.sh compares the image's migration journal with drizzle.__drizzle_migrations. When a migration is pending, it dumps to backups/pre-<tag>-<date>.dump and refuses to start the new image if the dump fails.
  2. Expand, then contract, never in the same release. A release adds: tables, columns, constraints, a backfill. Removal (old columns, trigger) comes in a later release, at least a week after the expand ran in production, once a verification query returns zero differences and a fresh dump was taken.
  3. No value is changed without a copy. Every fix-up (normalizing an address, nulling an orphan reference, rounding a float) first copies the old value into remediation_log(migration, table_name, row_key, column_name, old_value jsonb, logged_at). That table stays until the owner drops it (proposal: end of the academic year).
  4. Rehearsed on production-shaped data. Before each schema PR, refresh staging from production (pseudonymized export, existing scripts), run the migration there, compare the fingerprints (rule 5), then promote.
  5. Fingerprint before and after. scripts/db-fingerprint.sql, read-only, prints per table: row count and checksums of the meaningful values (sum of points per grading table, count of released grades, count of non-null references…). Same output before and after, except where the migration says otherwise.
  6. Constraints are added NOT VALID, then VALIDATEd in the same migration (the tables are small, the lock is brief), each one preceded by the read-only audit query that proves production satisfies it.
  7. One schema change per production promotion, never while an evaluation is live (the deploy guard already refuses that), and the contract steps in a week with no project deadline.
  8. Every migration that is not additive joins the deployment guide's rollback list in the same PR.

4. Phases

Phase 0 — safety net and evidence (no schema change)

Step Content Risk
0.1 deploy.sh: automatic pre-migration dump, deploy refused if it fails (rule 1); deployment guide updated none
0.2 scripts/db-fingerprint.sql (rule 5) none
0.3 Timed restore drill: last dump into a scratch PostgreSQL, fingerprint compared with production's none
0.4 scripts/db-audit.sql, read-only, run once in production: the distinct values of every column Phase 3 constrains; addresses that are not normalized and the collisions normalizing them would create; float8 values with more than 2 decimals; orphan references (F3); parent mismatches (F2) none

The result of 0.4 decides each later fix-up: no violation means no fix-up. A collision (two roster lines that would become the same address) is listed for the owner, never resolved automatically.

Phase 1 — memory and PostgreSQL configuration

The VM already swaps. Tuning PostgreSQL alone would take memory from the other services, so the VM grows first.

Step Content
1.1 Hetzner rescale, CPU and RAM only (the disk is kept, so scaling back stays possible), to 2 vCPU / 4 GB at least. One reboot (~2 min), outside any evaluation; it also applies the pending kernel
1.2 compose.prod.yml: shared_buffers=256MB, effective_cache_size=1GB, work_mem=4MB, maintenance_work_mem=64MB, shared_preload_libraries=pg_stat_statements, track_io_timing=on, log_min_duration_statement=500ms, log_lock_waits=on, idle_in_transaction_session_timeout=5min; stale comment (two PostgreSQL instances at ~50 MB) corrected. One PostgreSQL restart (seconds)
1.3 CREATE EXTENSION pg_stat_statements once per environment, by hand and documented: PGlite does not have it, so it cannot be a Drizzle migration
1.4 After a week of statistics: an application-side statement_timeout on the app's pool only (not pg-boss, not the backup, not migrations), set above the measured maximum (likely 30 s)

Phase 2 — the hot paths (additive)

Step Content
2.1 Read pg_stat_statements: which statement makes the ~17,000 daily updates of project_repos, and which makes the sequential scans of project_repos, evaluations, course_staff, questions
2.2 Indexes: project_repos(project_id), grade_dispatches(repo_id), attempts(user_id), answer_acceptances(item_id) (CREATE INDEX: tables are small, no CONCURRENTLY needed inside the migration transaction)
2.3 The no-op writers found in 2.1 write only when the value changes (WHERE col IS DISTINCT FROM $new)
2.4 Regression guard: a schemaHygiene.db.test.ts that reads the migrated catalog and fails on a foreign key without a covering index or a table without a primary key (explicit allowlist for the accepted cases)

Phase 3 — integrity constraints (additive)

0.4 found nothing to fix up, so Phase 3 and the indexes of 2.2 ship as ONE additive migration, with the hygiene test of 2.4: one promotion instead of five. 2.1 and 2.3 still wait for the statistics.

  • 3.1 State and role checks (F1). A CHECK (col IN (...)) built from the same TypeScript constant the code uses, so a new value forces a migration. First, the columns that carry an authorization or a state machine: users.role, course_staff.role, pool_members.role, sessions.kind, attempts.state, gradings.state/source, contestations.state, project_contestations.state, project_criterion_grades.state/source, projects.state, project_repos.provision_status, kiosk_pairings.state, launch_tickets.kind, course_pools.mode.
  • 3.2 Normalized addresses (F4). CHECK (email = lower(btrim(email))) on user_emails, enrollments, teacher_grants, after the fix-up of 0.4 (old values in remediation_log). users.email stays as the identity provider sends it.
  • 3.3 Consistent parents (F2), without any new column.
  • gradings(answer_id, attempt_id, item_id) → answers(id, attempt_id, item_id).
  • project_group_members(group_id, project_id) → project_groups(id, project_id).
  • project_repos(group_id, project_id) → project_groups(id, project_id) with ON DELETE SET NULL (group_id) (PostgreSQL ≥ 15, hand-written SQL if drizzle-kit cannot express the column list).

answers against its attempt's evaluation would need an evaluation_id column: left out, low value. - 3.4 Missing foreign keys (F3). ON DELETE SET NULL on the three grade run slots and attempts.last_item_id (no orphan in production, 0.4). attempts.shown_item_id keeps none: attempts_shown_ck ties it to shown_since, so a SET NULL of the item alone would break the check; the dwell closes the interval itself. push_receipts keeps no foreign key on purpose (direction project → github, N-DATA-03). project_criterion_grades.pass_id keeps none either: 0.4 found it pointing at a grade dispatch (4,898 rows) or at an evidence row (524), and 5,349 at a pass since forgotten (a reopen forgets its passes). It is the trace of the pass that wrote the row, not a reference to keep alive; its schema comment says so.

Phase 4 — splitting the catch-all tables (F7, F5)

The plan follows rule 2. Each split is one table whose primary key is the parent's id, in three releases:

  1. Expand. The migration creates the table and copies the columns (INSERT … SELECT, same transaction). The code now reads and writes the new table only. A trigger on the new table mirrors every write back to the old columns, so an older image (rollback) still reads current values. The old columns are neither written by the code nor dropped.
  2. Verify (≥ 1 week in production). A query compares old and new columns and must return zero rows. The fingerprint is unchanged.
  3. Contract. After a fresh dump: drop the trigger and the old columns, and add the migration to the rollback list.

project_repos (49 → ~33 columns), now:

  • project_repo_grades, owned by the grading side of the project module: teacher_points, teacher_max, teacher_comment, teacher_graded_by, teacher_graded_at, the six grade_adjust_*, released_points, released_max, released_grade, released_comment, released_adjustment_comment, with the grade_adjust_whole check.
  • The points become unconstrained numeric here, which fixes F5: exact, and never rounded. Every stored value has at most two decimals (0.4), but a numeric(6,2) would round a future computed value silently.
  • A trigger in each direction (new → old and old → new, each writing only what differs) keeps both copies equal through a rollback and the next roll-forward, with no manual step.
  • The human writes (grading screen) no longer contend with the machine's writes on the same row.

project_repos, later and only on evidence: the activity columns (last_commit_*, ci_status, sync_outcome*, the run slots) move only if 2.1 shows they are the hot writer. The deadline and protection columns stay: the 20 s tick's predicates (NEEDS_WORK) read them, and a join there would cost more than it saves.

projects (58 → ~44 columns):

  • project_job_leases(project_id, kind, leased_at, due_at, failures) in place of deadline_job_at, dispatch_job_at, group_sync_job_at, sync_job_at, group_sync_due_at, group_sync_failures. claimLeases already takes the column as a parameter, so the change is local, and a future lease needs no migration.
  • project_source_state (1:1): source_ahead_sha, source_ahead, source_pushed_at, source_heads, synced_at, sync_heads, sync_message, sync_message_at.
  • The configuration (strategies, modes, commands, criteria) stays in projects: it is what a project is.

project_grade_runs.points/max (float8, written from CI output) become unconstrained numeric by an ALTER COLUMN … TYPE numeric USING x::text::numeric (exact: the shortest round-trip text of the float, never the 15 digits of a plain ::numeric), after the same exact check.

Phase 5 — product decisions, then work

Item Proposal
F6 deletion Decided (§6.3): the services refuse deleting what holds work or grades; archive instead; ADR
F15 import_classroom Decided (§6.4): the legacy URL resolver goes, the schema is dropped (archived first)
F9 notifications A stored generated column kind (= payload->>'kind') and one dedupe_key; the ten partial indexes become one. Optional
F10 Document the meaning in the schema comment, or a nullable owner_user_id set for solo repositories only. Low priority
F11 nom/prenom Rename to family_name/given_name: pure churn, a non-additive migration; proposed not done
F8 activity entity A separate ADR; not in this plan
PITR Decided (§6.6): hourly dumps and copies (RPO 1 h); WAL archiving only if needed

5. Order and size

Phase PRs Production impact
0 2 (deploy dump + guide; fingerprint + audit scripts) none
1 1 PR + the rescale by the owner one reboot, one PostgreSQL restart
2.2, 2.4 and 3 1 (0.4 found nothing to fix up) brief locks on small tables
2.1, 2.3 1 none
4 expand + contract per split: 3 splits → 6, plus the project_grade_runs type contract steps in a week without deadlines
5 per decision —

Phases 0 and 1 can start right away. Phase 2 needs a week of Phase 1's statistics. Phase 4's contract steps wait for a quiet week (semester break at the latest).

6. The owner's decisions (2026-11-21)

  1. The plan, as ordered.
  2. The VM was rescaled to CPX22 (2 vCPU / 4 GB) by the owner the same evening; the runner VM went down to 16 GB, its slices re-installed.
  3. F6, deletion: refuse, no soft delete. A soft delete would add a deleted_at filter to every query and to staffAccess: one forgotten filter shows a "deleted" course again. Instead the services refuse to delete an evaluation with a submitted attempt or released grades, a project with a graded repository, a classroom or a course holding one; they offer the archive (which classrooms and projects have). A draft or an empty classroom stays deletable. A short ADR amends F-ORG-09.
  4. F15: the legacy heig-classroom URLs are no longer needed. The resolver (modules/legacy, which read import_classroom.id_map) goes, and the schema is dropped; its dump was archived first (internal notes, 2026-11-21, 61 KB). legacy_classroom_audit_log is audit history and stays.
  5. F9: later, with the next deduplicated notification kind. F10: the schema comment.
  6. PITR: an hourly dump first. RPO 1 h (48 hourly dumps, 30 daily, the off-site copy hourly too), the backup checks warning after 3 h. WAL archiving only if an hour proves too much.
  7. remediation_log is created only by a migration that changes a value, and kept one year (an academic year and its contestation windows).

7. Progress

Phase 0 (2026-11-21)

  • 0.1 deploy.sh dumps the database before a production deploy that carries a pending migration, and refuses the deploy if the dump fails (exit 4). Exercised against a fake compose: up to date (no dump), pending (dump), check failing (dump, fail closed), dump failing or empty (refused, checkout back to the running commit), retention (ten kept).
  • 0.2 scripts/db-fingerprint.sql: 4 s on production.
  • 0.3 scripts/restore-drill.sh, run on the application VM: a 24 MB dump in 5 s, restored in 7 s into a throwaway container, 129 of 130 lines identical; the odd one, scheduled_tasks, moved during the dump.
  • 0.4 scripts/db-audit.sql on production, its outcome:
  • Every state and role column holds only the values its TypeScript constant declares (3.1 can be added as is).
  • Addresses: none unnormalized, no collision (3.2 needs no fix-up).
  • Parents: no grading, answer, contestation, group member or group repository disagrees with its parents (3.3 needs no fix-up).
  • The grade run slots and attempts.{last,shown}_item_id: no orphan, none pointing to another parent (3.4 needs no fix-up). pass_id is not a reference (above).
  • float8 points of project_repos: none with more than two decimals, the largest 100. Correction (2026-11-21, after the review of #1192): this was first measured through ::numeric, which keeps only 15 significant digits. Measured through ::text::numeric (exact), project_repos is confirmed, but project_grade_runs.points holds 252 values with float noise (e.g. a sum like 0.30000000000000004). Every float8 → numeric conversion of the plan casts through text, into unconstrained numeric, never numeric(6,2).
  • project_repos: 213 rows hold a released snapshot, 16 an adjustment, none a teacher score (teacher_points/teacher_max never written in production).
  • import_classroom: id_map 899 rows, runs 1.

So remediation_log has nothing to hold yet. It is created by the first migration that changes a value, if one ever does.

Phases 1 and 4 (expand), and the backups (2026-11-21)

  • #1190, #1194, #1195: the pre-migration dump. The first deploy carrying a migration was refused by it: under rootless Docker backups/ belongs to a uid of the containers' namespace, so the dump is now written by the backup container, read back whole, mode 600. It then ran: production dumped (24 MB) before 0151.
  • #1192 (Phase 4, expand of project_repo_grades) in production: 213 rows, totals equal to the old columns, the verification query 0 rows. Its first version cast float8::numeric, which keeps 15 significant digits: caught by the review, cast through text since. The contract step comes a week after, at the earliest.
  • #1191 (Phase 1) in production after the rescale: shared_buffers 256 MB and the rest, pg_stat_statements created by hand, and the API survives a connection the server ends (guardPoolErrors).
  • #1193 (Phases 2.2, 2.4, 3, migration 0152) reviewed and rehearsed on a copy of production (28 constraints validated); the next promotion.
  • Hourly dumps (§6.6): the dump every hour (48 kept, the day's latest linked as the daily one), the off-site copy every hour at :15, prune keeping 48 hourly archives, the backup checks warning after 3 h (ADR-055 amended). The timer unit is a copy on the VM: re-installed by hand.