10. Cutover runbook (M8-05)

The operator's sequence for switching heig-classroom off and Quiz on: what to do from a week before T0 to the decommission, who does it, the command, the check that proves it worked and how to undo it. It replaces §6.5 B–E and §6.7 of 06-codespace-seb-infra.md, and is written for production as it stands on 2026-10-09. Rehearse it on staging first: M8-06 runs this page there and times it (§7).

Who is one of:

  • owner: the product owner. Only the owner may do these: the GitHub UI, the SWITCH registry, the uptime service, approvals, anything as srvstg, anything in /etc/caddy/conf.d/ (the agent's sandbox blocks it), and every go/no-go.
  • agent (srv): an agent over ssh srv@128.140.71.35, after the owner has said go for that step. Reading is always allowed. Writing to a production database or stopping a service needs the owner's go in the session.
  • teachers: through the owner.

Root SSH to the application VM is refused. srv may use sudo only for caddy validate and systemctl reload caddy. No step writes to a production database by hand: data changes go through the import or the product's own actions.

0. One-page checklist

Open decisions for the owner (each blocks the step named):

# Decision Blocks Suggested
O1 T0 date and window. D20's target week (2026-10-05) has passed. Pick a morning that passes §1.4, with normal notice (7 days) or short notice (2 days, see the timeline below). Example under consideration: Sunday 2026-10-11, 09:00 Europe/Zurich, at short notice. the announcement a morning with no deadline before that evening
O2 Organizations. Which classroom organizations still need Quiz's App installed and a Quiz classroom connected (§1.2)? the rehearsal (M8-06) install it on every organization of a live classroom; drop the archived and test classrooms in the mapping
O3 One final import or two. D26 plans a first import while classroom still runs, then a --final one. Between the two runs, both Apps act on the same repositories: Quiz's ticker on what was imported, classroom's on everything (the M8-01 note "from M3-04"). C3 one --final import at T0, if M8-06's measured freeze C1→C8 stays within the M8-03b threshold (below)
O4 Staff-seat repositories. ADR-077 asks the dry run to count the repositories classroom let its teachers accept. The import does not count them, so §1.3 gives the SQL. Import them (badged "Teacher") or leave them out? the mapping (T-3) import them: they are counted nowhere
O5 Deadline window. The --final pre-flight refuses a live assignment whose deadline (plus grace) falls within --window-hours of the run, 24 by default. The window only has to cover the freeze and the catch-up (C1→C8, ≤ 2 h by the M8-03b threshold) with a margin. When the next classroom deadline falls the same evening, 24 h would refuse a morning T0 for nothing: pass --window-hours 12 at C3, and use W=12 in §1.4. T0 24 h; 12 h when the next deadline is the same evening, at least 12 h after T0
O6 The import's runtime. The production image runs the import as node dist/import-classroom.js (#655, §1.6). M8-06 #655 merged and deployed
O7 The point of no return. D lasts one to two weeks. Settled 2026-10-14 (product owner): D was clean, E started that day (§5). E T0 + 7 days if C8 and D's checks are clean
O8 Roster options at C3. The D08 addendum (2026-10-05) made --missing-students report and --assistants skip the defaults, with the rosters fixed by hand before the final import. The production dry run of 2026-10-10 lists, under the defaults, 47 students absent from the Quiz rosters (TSA 15, MI-2026 21, VisIndus 6, Prog-A 3, Prog-D 2, Prog-C 1), 4 assistants without a seat, and 12 members of the group projects of TSA and VisIndus not placed. With --missing-students enroll --assistants staff (the options M8-06 rehearsed) nothing is left to settle; the price is 19 MI-2026 lines whose account already holds another line of the classroom (another address): they are created unclaimed with a conflict flag the teacher resolves (AU-21). C3 the explicit options, ROSTER below; by hand only if the teachers fix the 51 lines before T-1 h

D20 and D22 are settled (08-decisions.md); only their date (O1) and their inputs (O2, the mapping) remain.

The M8-03b threshold is set here, and 06 and the M8-03 card point to it. If M8-06 measures a freeze from C1 to C8 longer than 2 h, build M8-03b (a read-only flag in classroom) before T0. C3 alone is not the criterion.

The sequence. Each step has two dates: normal notice, then short notice in brackets. At short notice the rehearsal (M8-06) is the staging dry run, the day before T0.

As run: P to C8 on 2026-10-10 and 2026-10-11 (M8-06, M8-07 in PROGRESS.md, with their times), D from 2026-10-11 to 2026-10-14, E from 2026-10-14 (M9-01). The boxes below are the template, left unticked; PROGRESS.md is the record.

  • P: #655 (O6) deployed to production
  • T-7 [T-2]: T0 chosen (O1) and checked with §1.4; announcement 1 sent (appendix A)
  • T-7 [T-2]: the organization list (§1.2); teachers asked to install Quiz's App and connect their classrooms
  • T-5 [T-1]: M8-06 rehearsed on fresh dumps (§7), go written in PROGRESS.md; its personal-data copies deleted the same day (§5.1)
  • T-3 [T-1]: rosters fixed by hand (lists.missingStudents, lists.skippedAssistants) or O8 settled on the explicit options; mapping validated (D22); O3, O4 and O5 settled
  • T-1 [T-1]: a production dry run (§1.3), clean; §1.4 re-run; secrets checked (§1.5); backups checked and image tags recorded (§1.7); Quiz deploys frozen until C8 (§1.7); announcement 2 sent
  • T-1 h: §1.4 re-run
  • T0 C1: maintenance fragment, uptime probe paused, classroom deploys disabled, classroom app stopped
  • C2: classroom dump, Quiz pre-migration dump, scratch database restored
  • C3: --apply --final, exit 0, parity clean
  • C4: dropped (M8-04)
  • C5: workspace settings verified, nothing changed
  • C6: redirect fragment, check-classroom-redirects.sh green against production
  • C7: reconcile.repos, reconcile.grades, reconcile.deliveries run by hand
  • C8: smoke list green; uptime monitors switched; Quiz deploys unfrozen; "done" message sent
  • D: one to two weeks of observation (§4)
  • E / M9-01: 302 changed to 308, the final copy of classroom's data off the VM (as run: its last nightly dump on the owner's workstation, §5 step 2), every personal-data copy deleted, classroom removed, its App uninstalled last, repository archived

Shell helpers, used everywhere below. On the application VM, as srv (ssh srv@128.140.71.35):

export DOCKER_HOST=${DOCKER_HOST:-unix:///run/user/$(id -u)/docker.sock}
q() { (cd /srv/quiz && docker compose -f compose.prod.yml --env-file .env.prod --env-file .env.image "$@"); }   # Quiz
h() { (cd /srv/heig-classroom && docker compose -f compose.prod.yml --env-file .env.prod "$@"); }                # classroom
install -d -m 700 /srv/quiz/merge     # every cutover file: dumps, mapping, reports (they name people), §5.1

As srvstg (owner: sudo machinectl shell srvstg@):

export DOCKER_HOST=${DOCKER_HOST:-unix:///run/user/$(id -u)/docker.sock}
install -d -m 700 ~/merge
# compose.staging.yml caps `app` at 256 MB with a 192 MB heap, and `compose
# run` inherits the cap: the import dies of "heap out of memory" on
# classroom's data (M8-06, 2026-10-10). This override lifts it for the
# import's container only; the running staging app keeps its cap.
cat > ~/merge/import-override.yml <<'EOF'
services:
  app:
    mem_limit: 768m
    memswap_limit: 768m
    environment:
      NODE_OPTIONS: --max-old-space-size=640
EOF
s() { (cd ~/quiz-staging && docker compose -f compose.staging.yml -f ~/merge/import-override.yml --env-file .env.staging --env-file .env.image "$@"); }

The roster options of O8, passed to every dry run and to C3 so that the reports compare (empty after a by-hand fix):

ROSTER="--assistants staff --missing-students enroll"

The import (#655), in both shells. Its first argument is the compose helper (q as srv, s as srvstg), its second the cutover directory on the host (/srv/quiz/merge or ~/merge), and the rest are the import's flags:

imp() {
  local c=$1 dir=$2; shift 2
  # --user 0: under rootless Docker, container root is the host account
  # itself (srv or srvstg), the only one that may read and write the 700
  # cutover directory. The image's `node` maps to a sub-uid that cannot.
  # --source-db names a database on DATABASE_URL's server: no password on
  # argv. $SUPER_ADMIN_EMAIL (the --actor, an admin) is expanded by the
  # container's shell, from the environment's env file.
  "$c" run --rm --no-deps -T --user 0 -v "$dir:/merge" app sh -c \
    'exec node dist/import-classroom.js --source-db hgc_cutover \
       --mapping /merge/mapping.json --actor "$SUPER_ADMIN_EMAIL" "$@"' sh "$@"
}

1. Before T0 (T-7 to T-1, or T-2 to T-1 at short notice)

1.1 Rehearsal

M8-06 (§7) runs §2 on staging with fresh dumps of both databases and times every step. It needs #655 deployed. Its go comes before the production dry run: at normal notice by T-5, at short notice the day before T0. A no-go postpones T0, and a "postponed" note goes out.

1.2 Organizations still used by classroom (T-7 [T-2], agent (srv))

h exec -T postgres psql -U hgc hgc <<'SQL'
-- classroom's organizations and what each still carries
select o.login, o.github_org_id,
       count(distinct c.id) filter (where c.archived_at is null) as live_classrooms,
       count(distinct a.id) filter (where a.state = 'published' and a.archived_at is null) as live_assignments,
       count(distinct j.journal_id) as journals
from organizations o
join classrooms c on c.org_id = o.id
left join assignments a on a.classroom_id = c.id
left join classroom_journals j on j.classroom_id = c.id
group by 1, 2 order by 1;
SQL
q exec -T postgres psql -U quiz quiz <<'SQL'
-- where Quiz's App acts (installed, not suspended, active), with the connected classrooms
select o.login, o.github_org_id,
       o.installation_id is not null and o.suspended_at is null and o.status = 'active' as app_acts,
       count(l.classroom_id) as connected_classrooms
from github_organizations o left join github_classroom_links l on l.org_id = o.id
group by o.id order by 1;
SQL

Every login in the first list that has live classrooms needs app_acts = t and at least one connected classroom in the second list. A missing one is a task for its teacher: install Quiz's App ("All repositories") and connect the Quiz classroom from the classroom's Settings → GitHub (F-GH-02). The dry run (§1.3) gives the authoritative answer per classroom, as a mapping refusal:

  • "the Quiz classroom is not connected to GitHub; its teacher connects it to <org> first";
  • "… connected to X, not to the classroom's organization".

A journal of an organization where Quiz's App does not act is listed under Classroom journals ("imported pending").

The App must also subscribe to pull_request (M3-07). Owner: GitHub → Settings → Developer settings → GitHub Apps → heig-quiz → Permissions & events, compared with the table in github-app.md.

Rollback: none needed. Installing Quiz's App changes nothing for classroom (D23).

1.3 Dry runs (on staging with M8-06, then T-1 in production)

The mapping (owner, D22). Write /srv/quiz/merge/mapping.json in the shape of apps/api/scripts/import-classroom/mapping.ts: one row per classroom, archived ones included, each either target: {course, classroom} or drop: true. The first dry run prints every source classroom with its organization under Mapping: that output is the list to start from.

Staging dry run (M8-06, §7). Both dumps go through the inbox. First, as srv (agent):

h exec -T postgres pg_dump -Fc -U hgc hgc > /srv/staging-inbox/.hgc.dump.part \
  && chmod 640 /srv/staging-inbox/.hgc.dump.part && mv /srv/staging-inbox/.hgc.dump.part /srv/staging-inbox/hgc.dump
install -m 640 -g srvstg /srv/quiz/merge/mapping.json /srv/staging-inbox/mapping.json
# --keep-identities, after hgc.dump (it is refused without it): the import
# matches people by address and edu-ID identifier, which a normal export
# pseudonymizes (ADR-028, update 2026-10-11).
/srv/quiz/scripts/staging-export.sh --keep-identities

Then as srvstg (owner):

~/quiz-staging/scripts/staging-refresh.sh
s exec -T postgres psql -U quiz -d postgres -v ON_ERROR_STOP=1 \
  -c 'DROP DATABASE IF EXISTS hgc_cutover WITH (FORCE)' -c 'CREATE DATABASE hgc_cutover OWNER quiz'
s exec -T postgres pg_restore -U quiz -d hgc_cutover --no-owner --role=quiz --exit-on-error < /srv/staging-inbox/hgc.dump
cp /srv/staging-inbox/mapping.json ~/merge/
imp s ~/merge --dry-run --report-json /merge/dry-run.json | tee ~/merge/dry-run.txt; echo "exit ${PIPESTATUS[0]}"

The same day, delete the staging copies (§5.1).

Production dry run (T-1, agent (srv) after the owner's go). It writes in one transaction and rolls it back. It reads classroom through a scratch copy, so classroom stays untouched:

h exec -T postgres pg_dump -Fc -U hgc hgc > /srv/quiz/merge/hgc-dry.dump
q exec -T postgres psql -U quiz -d postgres -v ON_ERROR_STOP=1 \
  -c 'DROP DATABASE IF EXISTS hgc_cutover WITH (FORCE)' -c 'CREATE DATABASE hgc_cutover OWNER quiz'
q exec -T postgres pg_restore -U quiz -d hgc_cutover --no-owner --role=quiz --exit-on-error < /srv/quiz/merge/hgc-dry.dump
imp q /srv/quiz/merge --dry-run --report-json /merge/dry-run-prod.json | tee /srv/quiz/merge/dry-run-prod.txt; echo "exit ${PIPESTATUS[0]}"

What "clean" means, section by section of the report:

  • Refusals: none. A dry run lists them without refusing (exit 0); --apply would exit 2.
  • Pre-flight (source): every DATA check ok. The STATE checks read "would refuse --final" while classroom runs.
  • Mapping: every classroom resolved or dropped, and the teachers confirm the resolved course and classroom (D22).
  • Identity: ambiguous = 0.
  • To settle by hand: the missing students and skipped assistants are either fixed in Quiz's rosters by T-1 or accepted by the owner (D08 addendum: nothing is created for them).
  • Parity: no MISSING, no RED LINES. The GitHub-bound checks appear under "Checks not run".

ADR-077 count (O4): the repositories held by a staff member of their classroom.

h exec -T postgres psql -U hgc hgc <<'SQL'
select c.id, c.name, count(*) as staff_repos
from student_repos r join assignments a on a.id = r.assignment_id join classrooms c on c.id = a.classroom_id
where c.teacher_id = r.user_id
   or exists (select 1 from classroom_staff s where s.classroom_id = c.id and s.user_id = r.user_id)
   or exists (select 1 from enrollments e where e.classroom_id = c.id and e.user_id = r.user_id and e.staff)
group by c.id, c.name order by c.name;
SQL

Rollback: none needed. A dry run commits nothing; the scratch database stays until E (§5.1).

1.4 Choosing T0 (T-7 [T-2], re-run at T-1 and T-1 h; agent (srv))

Run on the VM with the helpers of §0. W is the --window-hours that C3 will pass (O5):

T0='YYYY-MM-DD HH:MM Europe/Zurich'      # the candidate (O1)
W=24                                     # or 12 (O5)
h exec -T postgres psql -U hgc hgc <<SQL
-- (1) classroom: live, unfrozen assignments with a deadline before T0 + W (the --final pre-flight)
select c.name as classroom, a.name, a.deadline_at at time zone 'Europe/Zurich' as deadline, a.grace_minutes,
       a.deadline_at + make_interval(mins => a.grace_minutes) > now() as grace_ahead
from assignments a join classrooms c on c.id = a.classroom_id
where a.state = 'published' and a.archived_at is null and a.frozen_at is null
  and a.deadline_at <= timestamptz '$T0' + make_interval(hours => $W)
order by a.deadline_at;
-- (2) classroom: review checkpoints due in [T0, T0 + W] (informative)
select a.name, m.name as checkpoint, m.due_at at time zone 'Europe/Zurich' as due
from assignment_milestones m join assignments a on a.id = m.assignment_id
where m.dispatched_at is null and m.due_at between timestamptz '$T0' and timestamptz '$T0' + make_interval(hours => $W);
SQL
q exec -T postgres psql -U quiz quiz <<SQL
-- (3) evaluations that may be live in [T0, T0 + 2 h]
select title, state, mode, opens_at at time zone 'Europe/Zurich' as opens, closes_at at time zone 'Europe/Zurich' as closes
from evaluations
where state in ('scheduled', 'lobby', 'running', 'paused')
  and coalesce(opens_at, timestamptz '$T0') < timestamptz '$T0' + interval '2 hours'
  and coalesce(closes_at, 'infinity') > timestamptz '$T0';
-- (4) project deadlines (plus grace) in [T0, T0 + 2 h]
select p.name, p.deadline_at at time zone 'Europe/Zurich' as deadline, p.grace_minutes
from projects p
where p.state = 'published' and p.archived_at is null
  and p.deadline_at + make_interval(mins => p.grace_minutes) > timestamptz '$T0'
  and p.deadline_at < timestamptz '$T0' + interval '2 hours';
-- (5) a repository's own deadline (plus its project's grace) in [T0, T0 + 2 h]
select p.name, r.id as repo, r.deadline_at at time zone 'Europe/Zurich' as own_deadline
from project_repos r join projects p on p.id = r.project_id
where p.archived_at is null and r.archived_at is null and r.frozen_at is null and r.deadline_at is not null
  and r.deadline_at + make_interval(mins => p.grace_minutes) > timestamptz '$T0'
  and r.deadline_at < timestamptz '$T0' + interval '2 hours';
-- (6) online projects (the workspace has no real class yet): expect 0
select count(*) as online_projects from projects where work_mode <> 'free' and archived_at is null;
SQL

The date passes when:

  • no row of (1) has grace_ahead = t. Such a row blocks the date: move T0, or, when the deadline is that evening at least 12 h after T0, set W=12 (O5);
  • every row of (1) with grace_ahead = f (already past, waiting for classroom's ticker to freeze it) is gone by T-1 h, or C3 will refuse deadlines;
  • (3), (4) and (5) return no row, and (6) returns 0.

Rows of (2) do not block. A checkpoint due during the freeze is dispatched by Quiz after the import, late; tell its teacher.

1.5 Secrets (§6.4), T-1, agent (srv)

Secret State on 2026-10-09 Check (counts, never values)
GITHUB_APP_ID, GITHUB_APP_SLUG, GITHUB_APP_PRIVATE_KEY_PATH + PEM, GITHUB_WEBHOOK_SECRET, GITHUB_APP_CLIENT_ID, GITHUB_APP_CLIENT_SECRET set, Quiz's own App (D23, M2-06) grep -cE '^GITHUB_(APP_ID\|APP_SLUG\|APP_PRIVATE_KEY_PATH\|WEBHOOK_SECRET\|APP_CLIENT_ID\|APP_CLIENT_SECRET)=.' /srv/quiz/.env.prod → 6; Administration → System status → GitHub App: no failure
CODESPACE_URL, CODESPACE_LAUNCH_SECRET set, the workspace is live (M6-04) grep -cE '^CODESPACE_(URL\|LAUNCH_SECRET)=.' /srv/quiz/.env.prod → 2
SUPER_ADMIN_EMAIL set; it is the import's --actor grep -c '^SUPER_ADMIN_EMAIL=.' /srv/quiz/.env.prod → 1
SCW_*, MAIL_FROM_NAME set; Quiz's sender is the one kept System status → Send me a test e-mail
LEGACY_CLASSROOM_COOKIE_SECRET not used: an old unsubscribe link gets a plain 302 to Quiz's settings (M8-02 drops the query) none
Engine VM PLATFORM_URL, issuers Quiz's instances since M6-04 none at the cutover
Keycloak, classroom's OIDC_*, COOKIE_SECRET not needed none
Vault (ADR-010) owner the age-encrypted copy of /srv/quiz/.env.prod and secrets/ is current; /srv/heig-classroom/.env.prod and its secrets/ are added (rollback, then E)

Nothing is staged at T0.

1.6 The import's runtime (prerequisite, O6)

PR #655 compiles the import into the production image. It runs as node dist/import-classroom.js, and --source-db <name> names a database on DATABASE_URL's server, so no password goes on argv. --help exits 0. M8-06 waits until #655 is deployed, then proves imp (§0) on staging with the image production runs.

1.7 Backups and the deploy freeze (T-1)

  • Owner: Hetzner Backups is enabled and its last slot is under 24 h old (Hetzner console). Optional: a manual VM snapshot on T0 morning.
  • Agent (srv): cat /srv/quiz/backup-status/last.json shows "ok":true from today. ls -lt /srv/heig-classroom/backups | head -3 shows today's hgc-<date>.dump.
  • Agent (srv): record what runs (the rollback precondition, §3):
{ h ps -q app | xargs docker inspect --format 'classroom {{.Config.Image}} {{.Image}}'
  echo "classroom commit $(git -C /srv/heig-classroom rev-parse HEAD)"
  echo "quiz $(cat /srv/quiz/.env.image)"; } | tee /srv/quiz/merge/images.txt
  • Owner: freeze Quiz's production deploys from T-1 until C8 is green. Approve no production deployment in that window; a run that waits is rejected or left waiting. C3 and the rollback assume that the image of images.txt is the one running.

1.8 Communication (owner)

Send appendix A at T-7 (or T-2 at short notice) and one day before (T-1), to classroom's teachers and students (classroom's e-mail list, Teams, the course pages). The teachers also get the mapping lines of their classrooms and the lists of §1.3 to fix (D22).

2. T0: freeze and migrate (target ≤ 1 h)

Target times, from M8-06 (2026-10-10, dumps of 6.5 MB and 7 MB): C2's dump, scratch database and restore under 1 min; C3's import 20 s, after the 10 min quiet (the production dry run of the same day: restore 5 s, import 14 s); the resolver and the smoke rows a few minutes. The freeze C1→C8 is bounded by the 10 min quiet and the smoke list, far under the M8-03b threshold: M8-03b is not built. Run the steps in order. A step whose check fails is a no-go: go to its rollback (§3).

C1 Freeze classroom (owner and agent (srv), ~5 min)

Owner, as srv, installs the maintenance fragment:

cp /srv/quiz/infra/caddy/classroom-maintenance.caddy /etc/caddy/conf.d/classroom.caddy \
  && sudo caddy validate --config /etc/caddy/Caddyfile --adapter caddyfile && sudo systemctl reload caddy
  • Owner: pause classroom's monitor on the uptime service.
  • Owner: disable classroom's deploys, so that a push to heig-classroom cannot restart it: gh workflow disable ci.yml --repo heig-tin-info/heig-classroom.
  • Agent (srv): stop the app and keep it stopped across a reboot (restart: always would bring it back). Postgres and backup stay up.
h stop app && h ps -aq app | xargs docker update --restart=no
date +%F-%H%M > /srv/quiz/merge/t0.txt

Check:

/srv/quiz/infra/caddy/check-classroom-redirects.sh --maintenance https://classroom.chevallier.io   # all rows OK
h ps app        # no running container

Rollback, step by step:

  1. Classroom's own fragment back: cp /srv/heig-classroom/Caddyfile /etc/caddy/conf.d/classroom.caddy, then validate and reload.
  2. h ps -aq app | xargs docker update --restart=always && h start app.
  3. gh workflow enable ci.yml --repo heig-tin-info/heig-classroom.
  4. Resume the monitor.

C2 Dumps (agent (srv), ~5 min)

TS=$(cat /srv/quiz/merge/t0.txt)
h exec -T postgres pg_dump -Fc -U hgc hgc > /srv/quiz/merge/hgc-pre-merge-$TS.dump
q exec -T postgres pg_dump -Fc -U quiz quiz > /srv/quiz/merge/quiz-pre-merge-$TS.dump
q exec -T postgres psql -U quiz -d postgres -v ON_ERROR_STOP=1 \
  -c 'DROP DATABASE IF EXISTS hgc_cutover WITH (FORCE)' -c 'CREATE DATABASE hgc_cutover OWNER quiz'
q exec -T postgres pg_restore -U quiz -d hgc_cutover --no-owner --role=quiz --exit-on-error \
  < /srv/quiz/merge/hgc-pre-merge-$TS.dump

There is no codespace step: classroom's portal has been stopped since M6-04, and its data is already archived on the engine VM (/root/classroom-codespace).

Check: ls -l /srv/quiz/merge/*-pre-merge-$TS.dump shows two non-empty files, and q exec -T postgres pg_restore -l < /srv/quiz/merge/quiz-pre-merge-$TS.dump | head -3 reads the Quiz dump. Then note the run count before C3:

q exec -T postgres psql -U quiz quiz -Atc 'select count(*) from import_classroom.runs' | tee /srv/quiz/merge/runs-before.txt

Rollback: nothing was written, so C1's rollback.

C3 The final import (agent (srv) after the owner's go)

Start it at least 10 minutes after C1's app stop: the pre-flight reads a task run or a webhook received within the last 10 minutes as a live classroom (QUIET_MINUTES).

imp q /srv/quiz/merge --apply --final --window-hours "$W" $ROSTER --report-json /merge/final.json | tee /srv/quiz/merge/final.txt; echo "exit ${PIPESTATUS[0]}"   # W as in §1.4 (O5), ROSTER as in §0 (O8)
Exit Report's first line Meaning Next
0 apply (final): applied committed, parity clean, journals ingested C5
0 nothing to do this exact import is already in the database Rows written all 0, then C5
1 (an error on stderr) the script failed (config, connection, a bug) authoritative: select count(*) from import_classroom.runs against runs-before.txt. Equal: nothing committed; fix and re-run if the cause is clear and quick, otherwise roll back. Greater: it committed, so read the report and decide as for exit 3 after a commit
2 REFUSED: nothing written a refusal: the mapping, an ambiguous identity, the pre-flight (source-stopped, queues-empty, webhooks-processed, deadlines, a DATA check) source-stopped within 10 min: wait and re-run. Anything else: roll back
3 RED LINES: … nothing written a parity red line inside the transaction, rolled back roll back
3 applied, with RED LINES listed a GitHub-bound check failed after the commit (journals re-ingested in error). The data stays owner decides: a journal error (its code) is fixed forward by a Refresh. Anything else: roll back

The red lines (each is a no-go):

  • a source row neither carried nor deliberately left out (MISSING);
  • courses, classrooms, github_organizations or github_classroom_links changed (D22 addendum);
  • a parity check red: repositories per project, sum(teacher_points), frozen grades, grade-run links, latest push receipt, groups per project, members per group, journals re-ingested error.

A task left running by a hard stop refuses source-stopped for good. Look at it in classroom's scheduled_tasks, then:

  1. Start classroom again and stop it cleanly (h start app, wait for the task, h stop app).
  2. Wait 10 min.
  3. Redo C2's classroom dump and restore.

queues-empty lists the jobs left in pgboss.job. M8-06 says whether classroom keeps delayed jobs there. If it does, the check needs a code fix before T0, not an override. Never edit the scratch copy to pass a check.

Check: exit 0, outcome applied, jq '.parity.redLines | length' /srv/quiz/merge/final.json → 0, and the run count is one more than runs-before.txt.

Rollback: §3, row "C3 committed".

C4 Codespace identity remap: dropped

M8-04 is dropped (owner, 2026-10-09). Classroom's portal never served a real class, and it has been stopped and disabled since M6-04. There is nothing to remap.

C5 Workspace settings: verify only (agent (srv))

CODESPACE_* are already set (§1.5), and Quiz's app does not restart. Check: curl -s https://quiz.chevallier.io/healthz → "status":"ok". An imported project is never online: the import refuses a non-free work mode (the work-mode DATA check).

C6 Redirects (owner, ~5 min)

Owner, as srv:

cp /srv/quiz/infra/caddy/classroom-redirect.caddy /etc/caddy/conf.d/classroom.caddy \
  && sudo caddy validate --config /etc/caddy/Caddyfile --adapter caddyfile && sudo systemctl reload caddy

Check (agent (srv)): /srv/quiz/infra/caddy/check-classroom-redirects.sh https://classroom.chevallier.io → every row OK, exit 0. Then click one real old link of an imported classroom: it lands on the Quiz classroom page (§6.6, M8-02).

Rollback: the maintenance fragment again (C1's command), then §3.

C7 Catch-up (owner in the UI, ~10 min)

Quiz's App saw every push during the freeze, but it acts only on repositories the import has made known. So Quiz now catches up from the repositories themselves (GR-14.3: a push reconciled after its deadline is late, hence T0 away from deadlines). In Administration → Scheduled tasks, press Run now on:

  1. reconcile.repos: heads, invitations, protection;
  2. reconcile.grades: the CI runs of quiet repositories;
  3. reconcile.deliveries: anything Quiz's App received and left unprocessed.

codespace.sync is not needed: no imported project is online.

Check (agent (srv)): q exec -T postgres psql -U quiz quiz -c "select key, last_status, last_run_at from scheduled_tasks where key like 'reconcile.%' order by key". All three show ok, with a last_run_at after T0.

Rollback: none of its own. The tasks are idempotent.

C8 Smoke (owner, with the agent reading logs; ~15 min)

# Action Expected
1 Sign in with edu-ID as a teacher of an imported classroom the classroom shows its projects, journal and roster
2 A student account with a classroom GitHub link: Settings the GitHub account is shown linked (the import carried it)
3 A test push to the test organization's repository (heig-quiz-classroom, TestCourse-A) a webhook_deliveries row with processed_at set within a minute: select event, received_at, processed_at, error from webhook_deliveries order by received_at desc limit 5
4 The teacher's project page of an imported project repositories, scores and states equal classroom's (same ids): one spot check with §4's SQL
5 An old URL: https://classroom.chevallier.io/classrooms/<old id> 302 → /legacy/classroom/… → the Quiz classroom
6 System status → Send me a test e-mail received
7 An imported journal page as a student it renders; select sync_status, count(*) from classroom_journals group by 1 shows no error
8 Ruleset bypass (I57): on one imported repository, GitHub → Settings → Rules → hgc-protect / hgc-deadline-lock Quiz's App can act. If only classroom's App is a bypass actor, the owner adds heig-quiz and records it
9 q logs --since 30m app \| grep -iE 'error\|warn' \| tail -50 nothing new beyond known noise

Then, owner:

  • uptime service: delete classroom's /healthz monitor (it now answers 410). Quiz's monitor is unchanged. Optional: a monitor on https://classroom.chevallier.io/ that expects 302.
  • Quiz's production deploys are unfrozen.
  • the "done" message (appendix A).
  • PROGRESS.md: the M8-07 row, timings, outcome.

3. Rollback

Precondition: /srv/quiz/merge/images.txt (§1.7) names the classroom and Quiz images and commits that ran. /srv/heig-classroom stays untouched until E, and classroom's App never moved.

What no rollback undoes. Quiz's App acts on GitHub from C3 on, and nothing reverses those actions:

  • bot commits (deadline commits, protected-file reverts);
  • deadline locks (hgc-deadline-lock rulesets);
  • sync branches and their pull requests;
  • review dispatches;
  • the invitations and protection of reconcile.repos;
  • C8's bypass changes.

Classroom, once back, starts from that state.

Quiz is not frozen. Between C2 and a restore of the pre-migration dump, everything else written in Quiz is lost: evaluations, attempts, pages, settings. That is why §1.4 keeps T0 free of evaluations, and why the restore is only for the first hours.

Stage Rollback Who
Before T0 nothing to undo; send a "postponed" note owner
C1, C2 C1's rollback owner, agent (srv)
C3 failed, nothing committed (the run count equals runs-before.txt) C1's rollback. Quiz is unchanged owner, agent (srv)
C3 committed, before C6 maintenance stays; stop Quiz's app, restore quiz-pre-merge-$TS.dump into a recreated database (deployment.md §6, Restore), start it; then C1's rollback. Quiz loses what was written since C2 agent (srv) after go
After C6, before the point of no return maintenance fragment again. Then either the pre-migration restore above (it loses every Quiz write since C2, so use it only within hours) or keep Quiz's data and stop Quiz acting on the imported projects. For the latter, see the steps below the table. Then C1's rollback; classroom's own App redelivers what it missed (GET /app/hook/deliveries). The cost grows daily: keep D short owner decides
After the point of no return (E) fix forward only —

Keeping Quiz's data after C6. There is no bulk archive path: the product archives one project at a time (F-PROJ-16, which also stops its groups through stopProjects).

  1. Agent (srv) counts the imported projects that are not yet archived (read-only): q exec -T postgres psql -U quiz quiz -Atc "select count(*) from projects where archived_at is null and id in (select target_id from import_classroom.id_map where source_table = 'assignments')".
  2. The owner archives each of them in the UI (project → Settings → Archive). Each archive is audited.
  3. The writes staff made in Quiz to imported data since T0 (audit_log) are replayed into classroom by hand.

4. D: observe (1–2 weeks)

Redirects stay 302: browsers cache 301 and 308. Classroom stays stopped and intact, and hgc_cutover stays for the spot checks. Daily, the agent (srv) runs these checks and reports to the owner:

q exec -T postgres psql -U quiz quiz <<'SQL'
-- webhooks failed or stuck since yesterday
select event, count(*) filter (where error is not null) as failed,
       count(*) filter (where processed_at is null) as unprocessed
from webhook_deliveries where received_at > now() - interval '1 day' group by 1 order by 1;
-- imported journals not healthy
select sync_status, count(*) from classroom_journals cj
join import_classroom.id_map m on m.target_id = cj.classroom_id and m.source_table = 'classroom_journals'
group by 1;
-- scheduled tasks in error
select key, last_status, last_run_at from scheduled_tasks where last_status = 'error';
SQL
q logs --since 24h app | grep -ciE 'error'      # read them if the count grows

Parity spot check (ids are kept): pick a project id and compare classroom's frozen copy with Quiz.

P=<project id>
q exec -T postgres psql -U quiz hgc_cutover -c "select count(*), count(frozen_grade_run_id), sum(teacher_points) from student_repos where assignment_id = '$P'"
q exec -T postgres psql -U quiz quiz -c "select count(*), count(frozen_at), sum(teacher_points) from project_repos where project_id = '$P'"

Also watch:

  • /healthz stays "attention":false;
  • the GitHub App's Advanced → Recent Deliveries shows no non-2xx (owner);
  • teachers' reports;
  • the VM's memory (I53): it should drop, since classroom's app no longer runs.

Go for the point of no return (owner, O7): no rollback-worthy issue is open, and D's checks have been clean for three consecutive days.

5. E / M9-01: point of no return and decommission

Started 2026-10-14 (the product owner's go, O7). In this order. Each step is the owner's unless it says otherwise. Which steps are done is the M9-01 row of PROGRESS.md.

  1. Permanent redirects. Change 302 to 308 in infra/caddy/classroom-redirect.caddy (a PR, by an agent; done in M9-01's PR). legacyRule's own 302s depend on identity and stay. Install the fragment as in C6 and run check-classroom-redirects.sh, updated in the same PR.
  2. Final dump, encrypted, off the VM (agent (srv) makes it; the owner holds the key and the destination): h exec -T postgres pg_dump -Fc -U hgc hgc | age -r <owner's age recipient> > /srv/quiz/merge/hgc-final-$(date +%F).dump.age. The owner copies it to the vault's storage, then checks that it decrypts and that pg_restore -l reads it.

As run on 2026-10-14, a deviation decided by the product owner: no new dump and no age copy in the vault. Classroom's app had been stopped since C1, so its last nightly dump, /srv/heig-classroom/backups/hgc-2026-10-14.dump (taken 2026-10-14 08:33 UTC), is final. The owner copied it by scp to their workstation and checked its sha256 on both sides (fde6b3a3217f59d2f0ddf0c880ba9120f6d245b422eb98c5429ab79b5bcd7242). The off-site borg archives (deployment.md §6, The off-site copy) also hold classroom's dumps until their retention (about three months) prunes them; push.sh no longer copies /srv/heig-classroom/backups. 3. Personal-data copies of the cutover (agent (srv), the same day as step 2): the deletions of §5.1, production rows. 4. Remove classroom's stack (agent (srv) after go): - h down -v removes the containers and the pgdata and keycloak-data volumes; - rm -rf /srv/heig-classroom; - remove the line command="/srv/heig-classroom/deploy.sh" from /home/srv/.ssh/authorized_keys.

Quiz keeps its own copy of the edu-ID key (/srv/quiz/secrets/eduid-private-key.pem): never revoke that JWK. 5. CI and registry: delete the DEPLOY_SSH_KEY secret and the DEPLOY_USER variable of heig-tin-info/heig-classroom, and delete the GHCR package heig-classroom (GitHub → organization → Packages). 6. edu-ID: in the SWITCH Resource Registry, remove classroom's redirect URI (https://classroom.chevallier.io/app/auth/callback), and its client if it is a separate one. Quiz's client and the shared key stay. 7. Engine VM (root): delete /root/classroom-codespace (M6-04's archive of classroom's portal) and /etc/codespace/github-app.pem if it remains. 8. DNS and fragment: keep classroom.chevallier.io and the redirect fragment for at least a year. 9. Classroom's GitHub App, last: uninstall hgc-prod from every organization, then delete the App. 10. Archive heig-tin-info/heig-classroom (gh repo archive heig-tin-info/heig-classroom). 11. Close: ADR-035 had #143 close at this step, but it was closed early, on 2026-10-05, as "not planned". Comment on it with the decommission's PR, then mark M9-01 done in PROGRESS.md.

As run, 2026-10-14/15: every step done by the owner, the agent's production steps being refused to it by its permission rules; step 5 partly — the repository was archived first, so its secret and variable stay, inert; step 6 as the deletion of the separate resource « HEIG Classroom ». The detail is the M9-01 row of PROGRESS.md.

5.1 Personal-data copies

Every copy the cutover makes holds students' names, addresses and grades. Until it is deleted it is unencrypted at rest: only modes 700/640 and the account boundaries protect it.

Copy Where Deleted by Deadline Command
staging scratch database hgc_cutover in staging's PostgreSQL owner (srvstg) the day of each staging dry run and of M8-06 s exec -T postgres psql -U quiz -d postgres -c 'DROP DATABASE IF EXISTS hgc_cutover WITH (FORCE)'
staging cutover directory ~srvstg/merge owner (srvstg) same day rm -rf ~/merge
inbox copies /srv/staging-inbox/hgc.dump, mapping.json agent (srv) same day rm -f /srv/staging-inbox/hgc.dump /srv/staging-inbox/mapping.json
production scratch database hgc_cutover in Quiz's PostgreSQL agent (srv) E, step 3 q exec -T postgres psql -U quiz -d postgres -c 'DROP DATABASE IF EXISTS hgc_cutover WITH (FORCE)'
production cutover directory /srv/quiz/merge (dumps, mapping, reports) agent (srv) E, step 3, once the final copy is verified (it keeps what must be kept; as run, the dump of step 2 on the owner's workstation), after the owner copies the directory locally if wanted rm -rf /srv/quiz/merge

The staging import also wrote classroom's data into staging's own Quiz database, which the --keep-identities export left with production's real identities, and that export's quiz.dump stays in the inbox. Two steps remove both the same day, after the inbox copies above:

  1. The agent (srv) runs /srv/quiz/scripts/staging-export.sh (no flag), so that the inbox holds a fresh, pseudonymized production copy without the import.
  2. The owner (srvstg) runs ~/quiz-staging/scripts/staging-refresh.sh.

6. Appendix A: announcements

The first announcement goes out at T-7, or at T-2 at short notice. Fill in the placeholders: <jour> <date>, <heure> (T0), <échéance> / <deadline> (the day the teachers must be connected by: T-3, or T-1 at short notice).

First announcement (fr)

Objet : Classroom déménage dans Quiz le ,

Bonjour,

Le , de à , classroom.chevallier.io sera en maintenance puis remplacé par Quiz (quiz.chevallier.io). Vos projets, dépôts, notes et journaux y seront repris tels quels ; vos anciens liens mèneront à Quiz.

Ce que vous avez à faire : rien, si votre compte GitHub est déjà lié dans classroom. Sinon, liez-le dans Quiz (Paramètres → GitHub) après la bascule. Évitez de pousser pendant la maintenance : un push est conservé, mais il n'est pris en compte qu'après.

Enseignant·es : installez l'application GitHub de Quiz sur votre organisation et connectez vos classes Quiz (Classe → Paramètres → GitHub) avant le <échéance>, puis validez la table de correspondance que vous recevrez.

First announcement (en)

Subject: Classroom moves into Quiz on ,

Hello,

On , from

What you need to do: nothing, if your GitHub account is already linked in classroom. Otherwise, link it in Quiz (Settings → GitHub) after the switch. Avoid pushing during the maintenance: a push is kept, but only counted afterwards.

Teachers: install Quiz's GitHub App on your organization and connect your Quiz classrooms (Classroom → Settings → GitHub) before , then validate the correspondence table you will receive.

One day before: the same text, headed "Rappel : demain" / "Reminder: tomorrow". After C8: "La bascule est faite : utilisez désormais quiz.chevallier.io." / "The switch is done: use quiz.chevallier.io from now on."

7. M8-06: the rehearsal on staging

This is §2 on staging, timed, with a fresh dump of both databases and the image production runs. It needs PR #655 deployed. At short notice it runs the day before T0. The owner works as srvstg unless a step says otherwise.

  1. Agent (srv): the dumps and the mapping into the inbox (§1.3, Staging dry run, first block). Note the time: it stands for C1.
  2. staging-refresh.sh (of the --keep-identities export), then hgc_cutover restored (§1.3, second block, up to pg_restore). Time it as C2.
  3. imp s ~/merge --dry-run --window-hours "$W" $ROSTER, then imp s ~/merge --apply --final --window-hours "$W" $ROSTER (O5, O8), with the s helper of §0 (the memory override: without it the import dies of "heap out of memory" after ten seconds, exit 139). Time both. The dump comes from a running classroom, so the STATE checks see a live source frozen in the copy:
  4. source-stopped passes once the copy is 10 minutes old;
  5. a job caught in pgboss.job or a task caught running refuses queues-empty or source-stopped for good;
  6. a near deadline refuses deadlines.

Record each such refusal and check that it is only that. Then rehearse with --apply alone. Never edit the copy to pass. 4. The same command again: expect nothing to do (idempotence). 5. The resolver on the imported data: open https://quiz.dev.chevallier.io/legacy/classroom/classrooms/<old id> and an old project link. Both land on the Quiz pages. M8-03 already checked the fragment itself. 6. Walk C8 rows 1, 4 and 7 with an allow-listed account (LOGIN_ALLOWLIST), and time the end of it as C8. The account must reach the imported classrooms: an edu-ID sub is pairwise per sector (user, issuer and the client's sector_identifier_uri), so a staging client registered under its own sector gets another sub than production's for the same person, and a login on staging after a refresh creates a NEW account, with no seat, next to the copied one (M8-06, 2026-10-10: the resolver answered 404 and the course list was empty until Super Powers were switched on). Either the staging client shares production's sector identifier (deployment.md §8; requested from SWITCH on 2026-10-10) or the tester switches Super Powers on (ADR-054). 7. Re-scrub, so staging's ticker leaves the imported projects alone: s exec -T postgres psql -U quiz -d quiz -v ON_ERROR_STOP=1 < ~/quiz-staging/scripts/staging-scrub.sql. 8. Delete the personal-data copies (§5.1, staging rows), the same day. 9. Record in PROGRESS.md, Rehearsal log: the dump date, the durations (restore, import, C1→C8), the parity summary and go/no-go. Fill in §2's target times.

Expected on staging, not a no-go:

  • staging's App acts on no production organization (N-SEC-18), so the journals the import creates end at sync_status = error with the code forbidden ("the classroom's organization has no installation"): the post-commit ingestion ran and was refused. journals re-ingested reports each as red, the import exits 3 after the commit, and the same journals are red again on the idempotence run. It is the "journal held by the missing installation" of the no-go list below, not a no-go. A journal the Quiz classroom already had is kept as it is and reads ok;
  • the dry run lists the GitHub-bound checks under "Checks not run";
  • C8's GitHub rows (2, 3 and 8) cannot be walked.

No-go:

  • a red line other than a journal held by the missing installation;
  • a refusal other than the STATE ones above;
  • an ambiguous identity;
  • a measured freeze C1→C8 over 2 h. Then build M8-03b (the read-only flag) before T0, or split the import as D26 planned (O3).